Construction Updates
What’s Happening on Site
We know construction can be disruptive sometimes. To help you plan ahead, here are a few quick updates about our OH2 development and what you can expect.
Construction Hours
Data Center Campus Construction Hours:
Monday – Friday: 6 AM to 8 PM ET
Saturday: 6 AM to 8 PM ET
Stay Informed
For construction or safety concerns, please contact us.
Key Monthly Activity
MAY 2026
-
Strip and grade for trailers / laydown / mechanical yard
-
Install temporary construction fencing
-
Stone laydown / trailers / mechanical yard
-
Build access roads
-
Earthwork continues
JUNE 2026
-
Begin underground storm and utility work
-
North site grading and building pad prep
JULY 2026
-
Mobilize for off-site utilities and start sanitary piping
AUGUST 2026
-
Underground utility installation
-
North Building pad preparation
© 2026 Vantage Data Centers. All rights reserved.