Key Monthly Activity

MAY 2026

  • Strip and grade for trailers / laydown / mechanical yard
  • Install temporary construction fencing
  • Stone laydown / trailers / mechanical yard
  • Build access roads
  • Earthwork continues

    JUNE 2026

    • Begin underground storm and utility work
    • North site grading and building pad prep

    JULY 2026

    • Mobilize for off-site utilities and start sanitary piping

    AUGUST 2026

    • Underground utility installation
    • North Building pad preparation